34 projects between 2011 and 2025, all for the public sector in Basra.

public projects delivered
34
Contract value
142.5bn IQD
Roads built and rehabilitated
80+km
Years on record
2011-2025

Projects per year

  1. 6
  2. 4
  3. 9
  4. 9
  5. 4
  6. 1
  7. 1
Projects per year
YearRoads and bridgesMunicipal worksSchools and buildingsElectrical worksOtherTotal
2011321006
2012400004
2013810009
2019243009
2022030014
2023000101
2025000101
  • Roads and bridges17
  • Municipal works10
  • Schools and buildings4
  • Electrical works2
  • Other1

Road length, running total

Road length, running total
YearAdded in the year, kmRunning total, km
20115.85.8
201214.820.6
201353.273.8
201910.183.9
20220.083.9
20230.083.9
20250.083.9

Only projects with a recorded length are counted.

The charts show the whole record. The filters below do not change them.

Field of work

Period

17 of 34 projects

Reset filters

2019

2 projects

  • Construction and maintenance of roads, bridges and culverts in Abu Al-Khaseeb district

    Field: Roads and bridgesArea: Abu Al-Khaseeb

  • Construction of roads in the Al-Huwaita area, 10.075 km

    Field: Roads and bridgesArea: Al-Huwaita10.075 km

2013

8 projects

  • Construction of the Umm Masjid roads in Al-Deir sub-district, 7.25 km

    Field: Roads and bridgesArea: Al-Deir sub-district7.25 km

  • Construction of the Al-Nakhailat village roads (completion) and secondary roads in Al-Kubayya, Al-Imam Al-Qaim sub-district

    Field: Roads and bridgesArea: Al-Imam Al-Qaim sub-district7.1 km

  • Construction of secondary roads in the villages of Al-Saib, Al-Shati, Al-Alwa, Bait Salman, Bait Abbad and Jannah, Al-Imam Al-Qaim sub-district

    Field: Roads and bridgesArea: Al-Imam Al-Qaim sub-district7.95 km

  • Construction of roads in Al-Naeem, East Al-Subaih, Al-Hamdawi, Mouzat Al-Khait and Nahr Basha, and maintenance of the road between the Al-Hamdawi and Souleekh junctions, 700 m

    Field: Roads and bridgesArea: Al-Naeem, Al-Hamdawi and Nahr Basha0.7 km

  • Construction of the Muzairia roads in Al-Qurna district and the Bait Dirjal road north of Muzairia

    Field: Roads and bridgesArea: Muzairia, Al-Qurna7.7 km

  • Paving of the Al-Hawafiz roads: Bait Badi, Bait Hanyan and Bait Hazza, Al-Awwad and Al-Batoush, Al-Mafati

    Field: Roads and bridgesArea: Al-Hawafiz9.5 km

  • Construction of the Hussainiya Ahl Al-Bayt, Sayyid Karim and Al-Hajj Abbas roads in the Abu Gharb area, and the Bani Sakeen roads

    Field: Roads and bridgesArea: Abu Gharb5.95 km

  • Construction of the road from Humayun to Al-Jawabir bridge, 7 km

    Field: Roads and bridgesArea: Al-Imam Al-Qaim sub-district7 km

2012

4 projects

  • Construction of secondary roads in Al-Shuwaihin and Bahila, Al-Imam Al-Sadiq sub-district, 4.5 km (phase two)

    Field: Roads and bridgesArea: Al-Imam Al-Sadiq sub-district4.5 km

  • Construction of roads in Al-Shafi, 2.55 km

    Field: Roads and bridgesArea: Al-Shafi2.55 km

  • Construction of roads in the Hamrinan area, Al-Hartha sub-district, 4.45 km

    Field: Roads and bridgesArea: Al-Hartha sub-district4.45 km

  • Paving of the streets of Hamrinan 2, 3.33 km

    Field: Roads and bridgesArea: Hamrinan3.33 km

2011

3 projects

  • Construction of roads in Al-Imam Al-Sadiq sub-district (Al-Hajj Bulbul, Al-Matam road, Bait Sauda), 3 km

    Field: Roads and bridgesArea: Al-Imam Al-Sadiq sub-district3 km

  • Construction of Al-Sayrafa road, 1.95 km

    Field: Roads and bridgesArea: Al-Imam Al-Qaim sub-district1.95 km

  • Construction of the Bait Al-Hajj Ati and Al-Hajj Jaid roads, 850 m

    Field: Roads and bridgesArea: Al-Shafi0.85 km